Geotechnical Drilling Program
Location
Alberta,
Canada
Contract Value
$78,000
Actual cost
$78,000
Date of completion
6/1/2026
—
6/11/2026
Project Overview
Forged Drilling completed a comprehensive geotechnical and environmental investigation to characterize subsurface conditions and groundwater, supporting engineering design, environmental assessment, and informed decision-making for future site development.
Drilling Services Provided
Forged Drilling completed a geotechnical and environmental drilling program using a hollow-stem auger rig, drilling 12 boreholes to 15 m with standpipe piezometer installations. Services included SPTs, Shelby tube and PFAS sampling, environmental and geotechnical sampling, limited NQ rock coring, and coordination of CPT/SCPT testing. All monitoring wells were completed with flush-mounted protective covers.
Principal
Project Details:
- 12 hollow-stem auger boreholes drilled to a minimum depth of 15 m
- Standpipe piezometers installed in all boreholes with flush-mounted protective completions
- Geotechnical sampling in all boreholes; environmental sampling in 6 boreholes
- SPTs, Shelby tubes, PFAS sampling, and limited NQ rock coring
- 3 CPTs and 1 SCPT (to 30 m/refusal)