Environmental Drilling – Mine Site

Location

Saskatchewan,

Canada

Contract Value

$703,000

Actual cost

Date of completion

6/2/2025

—

7/5/2026

Project Overview

Forged was engaged to provide environmental research support related to a mine site in the area of Saskatchewan. The Forged team completed the installation of monitoring wells using a mud rotary drilling rig.


Drilling Services Provided

Forged Drilling was contracted to provide services by drilling and installing monitoring wells. Our team installed 6 monitoring wells at 3 different locations using a mud rotary rig. Sampling was completed using Shelby tubes and holes were backfilled using SPPA grouting mixture.

Principal
Project Details:

  • Mud Rotary Drilling at 5 locations
  • Each location had 3 monitoring wells
  • Drill and install a 2-inch monitoring well into the Judith River Aquifer (210m)
  • Drill and install a 2-inch monitoring well into the Empress Group Aquifer (120m)
  • Drill and install a 2-inch monitoring well into the Dundum Aquifer (50-70 m)