Energy

Phase 2 Power Project

Location

Alberta,

Canada

Contract Value

$1,194,123

Actual cost

Date of completion

3/6/2026

—

3/28/2026

Project Overview

The project is currently undergoing a comprehensive environmental and technical assessment. Forged Drilling was contracted to provide sonic and mud rotary drilling services to support subsurface characterization across the proposed project area.


Drilling Services Provided

Forged scope of work included the drilling and completion of 9 boreholes using a combination of sonic and mud rotary drilling methods. 5 boreholes were advanced using a sonic rig to depths of up to 100 m. The remaining 4 boreholes were drilled to depths of 180 m using mud rotary techniques with a Christianson wireline core system to obtain rock core samples. These boreholes included the installation of up to 60 m of 178 mm diameter surface casing. Installations comprised VWP and standpipe monitoring wells.

Principal
Project Details:

  • 5 Boreholes up to 100 m deep each and 4 Boreholes up to 180 m deep each
  • Sonic and Mud Rotary drilling methods
  • SPTs at 1.5m intervals
  • Instrumentation installed: standpipe piezometers and vibrating wire piezometers